MRD utilized in-stock heavy profile inflatable seals and in-stock steel, burning, welding, and fabrication resources to quickly fabricate the bypass. Cranes were utilized to attach to load-rated lifting points on the bypass to support the bypass water weight load during installation. The unit was shipped overnight to the customer and was installed immediately. The customer installed the bypass specifically to our installation procedures and were able to begin construction demolition and repair within a day. Work occurred on three shifts over two weeks including the pouring and set-up of critical concrete structures. After successful completion the bypass was removed and the customer was able to move on to the remainder of their construction schedule.